Part of the M25 junction 11 roundabout shuts 8pm Friday 20 to 5am Monday 23 November. A lane of the anticlockwise exit slip then closes for about three months.

This page lists the roadworks, road closures and rail changes affecting Woking from Thursday 19 November 2026, with what is booked up to early December. The biggest change is at M25 junction 11. Surrey County Council is closing the western section of the roundabout from 8pm on Friday 20 November to 5am on Monday 23 November.

Straight after that, from Monday 23 November, a lane closes on the anticlockwise exit slip at junction 11 for about three months. That is the slip drivers use coming off the M25 from the Heathrow direction.

On the A3, the northbound carriageway between Dennis and Burpham in Guildford closes every night to Sunday 22 November, 9pm to 6am. From Monday 23 November the A3 northbound between Wisley and Esher closes overnight instead.

Updated 19 November: the A3 Burpham nights and the Pyrford Road electricity works no longer lead the page. New: the date and length of the anticlockwise junction 11 slip lane closure, the A3 Wisley to Esher nights from 23 November, a lane closure on St Peter’s Way eastbound, new National Highways and register entries to 27 November, and South Western Railway’s Christmas changes on 27 and 28 December, when some trains start from Woking. This page draws on National Highways’ seven-day report (updated at 1.15pm today, covering Thursday 19 to Wednesday 25 November), Surrey County Council’s register and A320 scheme page, and South Western Railway’s November and December pages, all checked today.

M25 junction 11: weekend closure, then a three-month slip lane closure

Surrey County Council’s A320 scheme page, checked today, says it is closing the western section of the M25 J11 roundabout for one weekend, from 8pm on Friday 20 November to 5am on Monday 23 November. The closure is needed to build an additional lane in that section (Surrey County Council, A320 North of Woking improvements).

The council’s signed diversion runs:

  • along St Peter’s Way westbound
  • round St Peter’s roundabout to turn back
  • back to M25 junction 11

Junction 11 is the main way onto the M25 from Woking, via the A320 through Ottershaw. The council’s page does not say which arms of the roundabout stay open, so allow extra time that weekend.

From Monday 23 November, work starts on the anticlockwise exit slip. The council says:

  • a lane will be closed on that slip for approximately three months
  • cones and signs go in overnight on Sunday 22 November
  • the slip road itself stays open, so the junction can still be used
  • there “may be increased congestion around the junction”

The council adds that in the first week its team will be monitoring traffic and working out of sight in the verges, so it may not be visible at all hours.

The lane closure on the clockwise exit slip (the Gatwick to Heathrow direction) stays in place from 4 November until late February 2027. Both slips are getting a dedicated left-turn lane.

The work at junction 11 also enlarges and resurfaces the roundabout and upgrades the drainage, signals and street lighting. The finished roundabout will be fully signalised.

The A3 and the motorways, night by night

National Highways’ seven-day closure report, updated at 1.15pm on Thursday 19 November, covers Thursday 19 to Wednesday 25 November (National Highways seven-day closure report). The closures on roads Woking drivers use most:

Night What closes Hours
Thu 19 Nov M25 anticlockwise, junction 11 exit slip, for urgent carriageway repairs 10pm to 5.30am
Thu 19 Nov M3 eastbound, junction 3 to junction 2, carriageway closed for repairs 10pm to 5.30am
Thu 19 to Sun 22 Nov A3 northbound, Dennis to Burpham (Guildford), carriageway closed for structures work 9pm to 6am
Mon 23 to Wed 25 Nov A3 northbound, Wisley to Esher, carriageway and slip roads closed for joint replacement 10pm to 5.30am
Mon 23 to Wed 25 Nov A3 southbound, Dennis entry slip (Guildford), for structures work 9pm to 6am
Mon 23 and Tue 24 Nov M3 northbound, junction 3 entry slip (Lightwater), for maintenance 9pm to 6am
Mon 23 and Tue 24 Nov M3 westbound, junction 2, between the slip roads, for electrical works 10pm to 5.30am

The Wisley to Esher closure is the one most likely to catch Woking drivers heading for London. Wisley is the A3 junction with the M25 at junction 10, reached from Byfleet along the A245. National Highways says its diversion uses local authority and national roads.

The report only looks a week ahead, and a night listed today can be re-dated or dropped before it happens.

Live and booked in the borough

Surrey County Council’s register, checked today, lists 79 sets of works in Woking, covering “today until the end of next week” (Surrey County Council street works register, Woking). The newest booking starts on Friday 27 November, so treat anything after that as only partly covered.

The longer or busier entries:

Road Works Dates
Manor Crescent, Byfleet Gas (SGN) 3 November to 21 December
Thistledene, Byfleet and West Byfleet ward Gas (SGN) 23 November to 18 December
Bruce Close, Byfleet and West Byfleet ward Gas (SGN) 18 November to 15 December
Madeira Road, Pyrford Gas (SGN) 7 October to 8 December
Station Approach, Mount Hermon Highways (Surrey County Council) 23 November to 3 December
Dartmouth Avenue, Canalside Highways (Surrey County Council) 23 November to 5 December
St Johns Road, St John’s Gas (SGN) 26 November to 2 December
Blackness Lane, Mount Hermon Gas (SGN) 16 to 30 November
Campbell Avenue, Hoe Valley Highways (Surrey County Council) 31 October to 27 November
Kettlewell Hill and Summerhayes Close, Horsell Gas (SGN) to 27 November
Moor Lane, Hoe Valley Gas (SGN) 18 to 25 November
Guildford Road, Heathlands ward Highways (Surrey County Council) 9 to 23 November
Goldsworth Road, St John’s Water (Affinity Water) 19 to 23 November
Connaught Road, Heathlands Carriageway patching (Surrey County Council) 23 to 26 November
Chertsey Road, Byfleet and West Byfleet ward Water (Affinity Water) 24 to 26 November
Commercial Way, Canalside Electricity (UK Power Networks) 25 to 27 November
Oyster Lane, Byfleet Electricity (Eclipse Power Networks) 21 to 23 November
Parvis Road, Byfleet and West Byfleet ward Telecoms (Virgin Media) 19 and 20 November

Byfleet and West Byfleet has the most short jobs: BT on High Road, Green Lane Close and Sheerwater Road from 20 to 24 November, and Virgin Media on Madeira Road (23 to 25 November) and on Station Road and Station Approach (25 to 27 November). Knaphill has short Affinity Water and BT jobs between 19 and 27 November, including Nursery Road, Barley Mow Close, Staveley Way and Anchor Hill. In St John’s, Beacon Hill has BT and county works from 23 to 25 November.

The register gives the road, the promoter and the dates. It does not record whether a job means a full closure, temporary lights or a single lane. It also cannot show emergency works: utility companies can notify the council of a burst main or a gas leak up to two hours after work starts. Check the live map on the day.

Surrey’s utility roadworks page, checked on 12 November, listed Murphy Group’s electricity upgrade from West Byfleet primary substation towards Sheerwater, along Martyrs Lane, Woodham Avenue, Sheerwater Road and Woodlands Avenue, with completion given as “Autumn 2026” (Surrey County Council, utility roadworks). No Murphy permit in Woking is on the register this week.

Holloway Hill: the closure runs into 2027

This is the change that matters most if you drive north from Woking. The junction of Holloway Hill and Guildford Road, about six miles north of Woking near Chertsey, has been shut while a new roundabout is built. Surrey County Council says it will stay shut until early 2027 (Surrey County Council).

The reason given is the utilities. The council says moving pipes and services around tree root systems proved “more complex than expected”. It had planned to lay a concrete slab to protect the new services. That slab would later have to be broken up and removed, meaning another round of closures. The council has decided instead to keep the road shut and carry on.

There is still no through route or access for any vehicle. The signed diversion runs via:

  • Guildford Road
  • Chobham Road
  • Old Chertsey Road
  • Stonehill Road
  • back onto Holloway Hill

Surrey has changed the diversion to Hardwick Lane “in response to concerns raised by residents”. It now runs via Lyne Crossing Road, the northern section of Lyne Lane, Green Road (B389), Millhouse Lane, Thorpe Road (B388), Chertsey Green Road, Pyrcroft Road, Bell Bridge Road and Guildford Road (A320). Surrey’s temporary bus changes page, checked on 16 November, says the Carlone 593 is diverted via Almers Road, Ruxbury Road and Pyrcroft Road and cannot serve Hardwick Lane until the road reopens. Access to the White Lodge Centre is kept open down Holloway Hill itself. No traffic is allowed onto Holloway Hill from Guildford Road. Pedestrian access is maintained.

The finished junction replaces the two roundabouts at Holloway Hill and Little Green Lane with a single new one, with footpaths, cycle paths, crossing points, better street lighting and flood measures. The council expects to complete this phase in spring or summer 2027.

Ottershaw: surveys done, restart awaits planning sign-off

Holloway Hill is one phase of a scheme running the length of the A320 between Woking and the M25. Surrey County Council is delivering it with Runnymede Borough Council and Homes England, funded by the Housing Infrastructure Fund.

The council’s scheme page, checked today, says the Ottershaw works “remain temporarily paused”. It now adds that the tree and habitat survey and review work “is complete”. The required documents have been submitted to the county planning authority “for review and sign-off ahead of works restarting”. No restart date is given; the council says it will update residents once the next steps are confirmed.

The pause followed work on protecting the retained trees around the roundabout and restoring a small area of copse that was cleared by mistake. The Murray Road car park in Ottershaw is closed, with no timescale given.

The rest of the scheme:

  • St Peter’s roundabout signals are on, at all hours, and the traffic management around the roundabout has been removed.
  • A lane stays closed on St Peter’s Way eastbound, towards the M25, for works in the central reservation. The council says it may need to put traffic management back in future and will post details first.
  • There is a temporary 30mph limit on St Peter’s Way, in force while construction continues. It takes precedence over the 50mph markings already painted on the road, which only take effect when the temporary order is lifted.
  • M25 junction 11: the weekend closure of 20 to 23 November, the anticlockwise slip lane closure from 23 November and the clockwise slip lane closure to late February 2027 (above).
  • A320 Guildford Road by St Peter’s Hospital: Surrey’s bus page, checked on 16 November, still warns of “a series of evening and weekend closures” and says it “will be updated when the next closures are announced”. None is dated.

Overall completion is targeted for autumn 2027. Three elements were cut from the scheme on cost grounds: St Anne’s roundabout, Little Green Lane to St Peter’s Hospital roundabout, and St Peter’s roundabout to Ottershaw roundabout.

Trains: Barnes closure on Sunday 22 November, and Christmas

South Western Railway’s November and December engineering works pages were checked today (South Western Railway, November engineering work; December engineering work).

Saturday 21 and Sunday 22 November: Petersfield to Portsmouth closed. Portsmouth trains via Guildford terminate at Petersfield, with buses on to Portsmouth via Havant.

Saturday 21 November: rugby at Twickenham. SWR runs extra trains via Twickenham and alters some Shepperton, Reading and Guildford via Cobham trains. Its list of changes does not include the main line through Woking.

Sunday 22 November: Barnes area closed. SWR says:

  • Waterloo to Woking trains via Staines will start from Kew Bridge.
  • Waterloo to Guildford stopping trains via Woking “will be revised”.
  • Buses run between Clapham Junction and Twickenham via Richmond, and between Clapham Junction and Kew Bridge.

Also on Sunday 22 November, Ascot to Guildford trains start from Aldershot, with buses between Ascot and Aldershot.

Saturday 28 and Sunday 29 November: Eastleigh area closed. Waterloo to Weymouth trains will be diverted between Woking and Southampton Central, calling additionally at Guildford, Havant and Fareham.

Saturday 5 and Sunday 6 December: Petersfield area closed. Portsmouth trains via Guildford will terminate at Haslemere, with buses beyond.

Sunday 13 December: Clapham Junction to Barnes closed. Waterloo to Woking trains via Staines start from Barnes, and Waterloo to Guildford stopping trains via Woking are revised.

Sunday 20 December: Barnes to Feltham via Hounslow closed. Waterloo to Woking trains via Staines are diverted between Barnes and Feltham, calling additionally at Richmond and Twickenham.

Sunday 27 and Monday 28 December: Queenstown Road area. Queenstown Road station closes on both days and Earlsfield station on the Monday. On Monday 28 December, SWR says:

  • Waterloo to Alton and Basingstoke stopping trains will start from Woking
  • some Waterloo to Portsmouth Harbour trains via Guildford will start from Woking
  • some Weymouth trains will call additionally at Woking
  • Waterloo to Woking stopping trains will start from Wimbledon or Surbiton
  • buses run between Clapham Junction and Surbiton via Wimbledon

On the Sunday, Waterloo to Guildford stopping trains via Woking are revised. SWR has not yet published times for either day.

Also closed on foot

The second footbridge over the Hoe Stream in Woking Park stays shut. It closed in November 2025 over structural concerns and the council says it is no longer serviceable. The main wooden bridge, which links to the skate park and Elmbridge Lane, closed on 10 August for two weeks of refurbishment and was due to reopen by Friday 21 August. The council’s notice, published on 30 July and checked again on 16 November, has not been updated since, so we cannot confirm the reopening from it (Woking Borough Council).

Victoria Arch: why the town centre pinch point is staying

Every journey on the A320 through the town centre passes under Victoria Arch, the railway bridge by the station. The plan to fix it is dead rather than delayed. The £115 million Victoria Arch widening scheme was formally closed in October 2023. A project review had found costs rising by more than £50 million, and Homes England stopped funding it. The council’s own position, a Section 114 notice and debts around £2 billion, ruled out a rescue (Woking Borough Council; BBC News).

The council has now formally written the scheme off. Its September 2026 report on selling the Triangle site says there is “no legal obligation to continue to protect part of the site for the bridge widening scheme”, and that Network Rail “has indicated there is no appetite to proceed”. We covered that in our report on the Triangle site sale. Plan around the arch at peak times rather than waiting for it to change.

The key routes, and what they carry

  • A320 (Guildford Road / Victoria Way / Chertsey Road): the borough’s spine, Guildford to Chertsey through the town centre and Victoria Arch, and the main way to M25 junction 11. Carrying the roadworks above until autumn 2027.
  • A245 (Parvis Road / Byfleet Road): the eastern route through West Byfleet and Byfleet to M25 junction 10 and the A3.
  • A247: the north-south link through Sheerwater and West Byfleet towards Send and the villages.
  • A322 / A324: the western corridor past Knaphill and Brookwood towards Bracknell, Guildford and the M3.
  • The A3 skirts the borough’s south-east edge at Ripley and Wisley, reached via junction 10.

Parking, the station and the buses

If the roads are bad the calculation usually flips to the train. Woking station has a 590-space car park and the fastest trains reach Waterloo in 24 minutes (National Rail). Town centre car park tariffs and the cheaper edge-of-town options are in our guide to parking in Woking.

Where to check live conditions

Frequently asked questions

Is the M25 closed near Woking this week?

Not the main carriageway between junctions 9 and 12. National Highways’ seven-day report, covering 19 to 25 November, lists one overnight closure nearby: the anticlockwise junction 11 exit slip, on the night of Thursday 19 November, 10pm to 5.30am. Separately, Surrey County Council is closing the western section of the junction 11 roundabout from 8pm on Friday 20 November to 5am on Monday 23 November.

Is M25 junction 11 closed?

Part of it, for one weekend. Surrey County Council is closing the western section of the roundabout from 8pm on Friday 20 November to 5am on Monday 23 November, with a signed diversion along St Peter’s Way westbound and round St Peter’s roundabout. From Monday 23 November a lane of the anticlockwise exit slip closes for about three months, and one lane of the clockwise exit slip (from the Gatwick direction) is closed until late February 2027. Both slips stay open.

Is the A3 closed near Woking this week?

At night. National Highways lists the A3 northbound between Dennis and Burpham, in Guildford, closed from 9pm to 6am every night to Sunday 22 November. From Monday 23 to Wednesday 25 November the A3 northbound between Wisley and Esher closes from 10pm to 5.30am.

What roadworks are happening in Woking now?

Surrey County Council’s register listed 79 sets of works in Woking on 19 November. The longest are SGN’s gas works in Manor Crescent, Byfleet, to 21 December, in Thistledene from 23 November to 18 December, in Bruce Close to 15 December, and in Madeira Road, Pyrford, to 8 December. The county has highways works on Station Approach, Mount Hermon, from 23 November to 3 December (Surrey County Council).

How long is Holloway Hill closed for?

Until early 2027. Surrey County Council originally described it as a full six-month closure. It has extended it because moving utility services around tree roots proved more complex than expected. The council expects this phase of the scheme to finish in spring or summer 2027.

Have the Ottershaw roundabout works restarted?

Not yet. Surrey County Council’s scheme page, checked on 19 November, says the tree and habitat surveys are complete and the documents have gone to the county planning authority for sign-off. It gives no restart date.

What is the speed limit on St Peter’s Way at the moment?

30mph. Surrey County Council says a temporary limit is in force while construction works continue. It takes precedence over the 50mph markings painted on the road, which only apply once the temporary order is lifted.

Are trains from Woking affected?

On Sunday 22 November, South Western Railway says Waterloo to Woking trains via Staines start from Kew Bridge, and Waterloo to Guildford stopping trains via Woking are revised. On 28 and 29 November, Weymouth trains are diverted between Woking and Southampton Central. On Monday 28 December, Alton and Basingstoke stopping trains and some Portsmouth trains via Guildford start from Woking rather than Waterloo.

Sources

Closures and dates change at short notice, and emergency works do not appear on the register in advance. Check the live sources above before setting off. Checked against the sources above on 19 November 2026.